CHESTERFIELD — A once-in-a-lifetime decision is on the table: Where should Chesterfield’s future town offices and public safety complex be built?
Depending on the route chosen, taxes could go up anywhere in the ballpark of $15 to $400.
Town officials have narrowed the choice down to four scenarios, with price estimates and projections for the impact on taxpayers’ pocketbooks that were drawn up in partnership with DA Sullivan and Sons. The current step in the redevelopment timeline is to garner as much community input as possible.
There are many questions to consider. Most everyone agrees that the town needs new facilities, but where to put them and how to pay for them are tough questions to answer. A 40-year loan means lower taxes but more money spent overall, while a shorter, 20-year loan saves money but bumps up taxes.
Town officials presented the four options earlier this month during a meeting at Town Hall, with about 25 residents in attendance.
The town currently has $3.6 million in stabilization funds that would be spent regardless of the plan. It is currently unclear what grant opportunities may be available.
Two buildings, two locations
One of the four options includes erecting two buildings on two different sites, more specifically, demolishing the old town offices at 422 Main Road and using 6 North Main Road.
As presented, the new town office under this plan would total $3.3 million. That price includes an estimated $200,000 for demolition, but no price tag for purchasing land. The new public safety complex was pegged at $7.2 million.

In all, this plan would cost $10.6 million, but with the help of stabilization funds, the total cost is estimated to be $7 million.
As for taxes, a 40-year loan at 4.5% interest would see an average annual tax bill increase of $192. The total cost of the debt would be $15.3 million.
If a 20-year loan at 4% interest were selected, an average annual tax bill could go up by $396, with a total debt cost of $10.3 million.
Fuller barn?
The other three options all center around Select Board Chair Roger Fuller’s property next to the current town offices.
The anticipated price tag to buy Fuller’s property is $1.5 million, although a special committee would be formed to carry out negotiations. On the lot is a house and a 4,400-square-foot barn. The town could sell the house on the lot.
The second option is to renovate the first floor of the barn and put town offices on the second floor. A 2,400-square-foot addition would constructed on the building to accommodate a fire truck.
This plan is estimated to cost $8.6 million after stabilization funds have been spent. A 40-year loan with a 4.5% interest rate would bring the full price to $10.9 million and result in an anticipated tax bill increase of $30. A 20-year loan at 4% interest would raise taxes an average of $173 annually.
The third scenario is to have public safety on the first floor and offices on the second, with no addition. Instead, the barn would be renovated, with estimated total costs coming to $8 million.






Only $4.4 million would need to be financed. With a 40-year, 4.5% interest loan, taxes are expected to go up $15. With a 20-year plan, that number is expected to be $113.
The fourth scenario is to have the public safety complex exclusively in the barn, with town offices constructed at 422 Main Road, the site of the current town offices.

The total price tag would be $9 million, and the amount of financing needed would be $5.4 million.
A 40-year, 4.5% interest loan would create an expected annual tax hike of $64. A 20-year, 4% loan would raise taxes an average of $219 a year.
Concerns from residents
Residents at the informational meeting wanted more information. A handful of people did not like the idea of having town offices above the public safety complex, especially when it comes to parking.
Some thought repurposing the Fuller Barn would be the best decision for longevity, with the anticipated lifespan of the new complexes being 75 years. Others wanted more clarity about what grant opportunities may be available.
More information will come, town officials said, as they encouraged residents to make their voices heard. In the meantime, residents can rank their choices using sheets available at the town office, and eventually online.
Any approval for projects or to spend money would need to be approved in a Town Meeting vote.