NORTHAMPTON — Roadwork on Burts Pit Road caused some expected, and unexpected, temporary shutoffs of water on Thursday.

Department of Public Works Director Donna LaScaleia said that the department was sliplining two culverts on the road. She said that culvert work is done before repaving because “drainage is key to maintaining a roadway.”

LaScaleia said that a portion of the water main needed to be protected as the culvert work was done. She also said that nine houses on Burts Pit Road were notified ahead of time that they’d receive an interruption to their water service.

However, she said an unexpected problem with the valve to Woods Road resulted in the households on that road being without water service for about two hours without warning.

“It’s always our intention to avoid an emergency condition,” she said.

LaScaleia also thanked the residents for their understanding.

LaScaleia said that the Burts Pit road reconstruction will involve 9,213 linear feet of roadway and cost about $1.5 million.

“It’s a fairly significant reconstruction effort,” she said.

Thursday’s construction also involved closing Burts Pit Road for a portion of the day. The city will continue with culvert work on the road in the coming days, and there will be intermittent lane closures.